No plans yet to shift Franz Josef poo ponds
By local democracy reporter Brendon McMahon:
A short-term fix to protect Franz Josef's vulnerable poo ponds has been finished.
But there is no plan yet to shift the tourist hotspot's wastewater infrastructure away from the Waiho (Waiau) River.
The nearby river previously destroyed the ponds eight years ago, and local council authorities are again worried by its changing course.
Westland District Council announced Tuesday the completion of "unbudgeted" emergency work to extend and shore-up stopbanks at the Franz Josef sewerage treatment site, as the Waiho River begins to encroach.
The council authorised the new protection banks after a storm on January 20 saw the river radically change course, with 95% of its main flow running into the Tatare Stream northwest of the ponds.
Since then the main Waiho channel has been running hard against the Havill Wall stopbank immediately in front of the ponds.
The council has now lengthened its stopbank off the end of the Havill Wall and curved it around the end of the sewerage ponds site amid West Coast Regional Council concerns about the rapid avulsion in the area.
Chief executive Simon Bastion said the council's contractor Westroads and South Westland's Campbell Agriculture and Contracting "shored up" protection to the west of the ponds site.
It gave "breathing space" and responded to the Regional Council's immediate concern about the rate of the riverbed avulsion in that area, he said.
The $370,000 cost was "unbudgeted" at this stage.
"Getting that work in place has obviously given us a lot of surety short-term … we will be seeking external funding to alleviate the costs to ratepayers," he said.
At this stage there was no guarantee about reducing the cost to ratepayers, he said.
The Franz Josef poo ponds site has been a known weak point for council for years.
The wastewater ponds and treatment site has rebuilt once after the Waiho River swept through in the April 2016 flood, which also destroyed the nearby Scenic Group Mueller Wing hotel complex.
In the aftermath the district council decided against shifting its wastewater infrastructure and controversially commissioned what is now known as the Havill Wall to protect the area.
Asked by LDR if council has done anything at all to explore a new site, Bastion replied: "not yet".
"There's critical components to line up here in terms of where to next," he said.
"It really comes down to any funding or for council to approve in the next annual plan."
However, at this stage council did not even have a scope to present to ratepayers within the 2024-34 long-term plan but "the actual reality" would be a replacement timeframe of up to four years.
Bastion said council could not immediately rely on central Government plans to speed up the Resource Management Act process for critical infrastructure.
Regional council chief executive Darryl Lew this week warned the river has now "cut back" about 50m towards the ponds area.
In the meantime, council was continuing its north bank protection scheme to extend, widen and raise stopbanks from Franz Josef township to the ponds.
This included improving and linking in the Havill Wall - to eventually pass into regional council ownership from the district council.
Lew said his council was aware of water now filtering through the Havill Wall from the river including into the ponds area but it was not unprecedented.
"The Havill Wall is below standard but we've investigated what we need to do there, and the (improvement) work is programmed," he said.
"We're aware of the seepage through parts of the bank. Our banks in terms of design are not like North Island (protection) banks. They're largely gravel with tow rock … you inevitably get seep.
"We're monitoring it and we've got no immediate concerns."
Time to Tickle Your Thinker 🧠
If a zookeeper had 100 pairs of animals in her zoo, and two pairs of babies are born for each one of the original animals, then (sadly) 23 animals don’t survive, how many animals do you have left in total?
Do you think you know the answer? Simply 'Like' this post and we'll post the answer in the comments below at 2pm on the day!
Want to stop seeing these in your newsfeed? No worries! Simply head here and click once on the Following button.
Poll: As a customer, what do you think about automation?
The Press investigates the growing reliance on your unpaid labour.
Automation (or the “unpaid shift”) is often described as efficient ... but it tends to benefit employers more than consumers.
We want to know: What do you think about automation?
Are you for, or against?
-
9.5% For. Self-service is less frustrating and convenient.
-
43.2% I want to be able to choose.
-
47.2% Against. I want to deal with people.
Have you got New Zealand's best shed? Show us and win!
Once again, Resene and NZ Gardener are on the hunt for New Zealand’s best shed! Send in the photos and the stories behind your man caves, she sheds, clever upcycled spaces, potty potting sheds and colourful chicken coops. The Resene Shed of the Year 2026 winner receives $1000 Resene ColorShop voucher, a $908 large Vegepod Starter Pack and a one-year subscription to NZ Gardener. To enter, tell us in writing (no more than 500 words) why your garden shed is New Zealand’s best, and send up to five high-quality photos by email to mailbox@nzgardener.co.nz. Entries close February 23, 2026.
Loading…