291 days ago

KiwiRail accused of holding up vital flood protection work

Nicole Mathewson Reporter from The Press

By local democracy reporter Brendon McMahon:

Delays caused by KiwiRail are "a risk" to quickly advancing a flood protection wall for Hokitika, a council meeting has heard.

The flood resilience work is part of a staged project to protect the Hokitika residential area and the CBD under way since early 2023.

The first stage of work on the bank of the Hokitika River, behind Westland Milk Products, has already been completed.

The council hopes to have the next stage from the Hokitika River Bridge, along Gibson Quay and the Hokitika Industrial Railway, to Westland Milk Products completed by mid-year.

The project has been deemed "urgent" after the river was just a few millimetres from overtopping the old bank at Westland Milk Products in late 2022. This would have been catastrophic for the region's dairy industry and Hokitika's single biggest employer, as well as residents in the surrounding area.

Council infrastructure programme manager Scott Hoare said they had been liaising with KiwiRail over a level crossing impact assessment for some time.

"There is a risk of further delays to the resource consent for Stage 1b due to delays in receiving feedback from KiwiRail," Hoare told the West Coast Regional Council's Infrastructure Governance Committee on January 29.

Council consultant Davis Ogilvie had responded to the additional queries from KiwiRail, and the level crossing assessment had been provided, "however resolving these issues will likely further delay the start construction".

Hoare said the two level crossings, which give access to the Hokitika Riverbed, were "a low risk category".

"However, KiwiRail are still problematic to deal with in terms of their timely response," he said.

Offers to assist KiwiRail to make less work for them had not advanced.

"It's still becoming quite problematic with them … we're working alongside their corridor, however, in terms of affected party approval, there may be other options," Hoare said.

Infrastructure Governance Committee chairperson Frank Dooley said the delay was "pretty disappointing" and "bureaucracy gone mad".

"KiwiRail is a Crown-owned entity, you'd expect their processes to be better than that," Dooley said.

Councillor Peter Haddock asked if council could still proceed on the basis it already had the consent of all other parties "or do we really need KiwiRail?"

Hoare said the council had the option of changing the consent process to a limited notification.

However, it appeared KiwiRail were still working things through internally, "albeit it's very slow".

Council chief executive Darryl Lew said they could give KiwiRail the rest of this week to respond.

"If they don't we will proceed to limited notification. If they come back with written approval, that's when the limited notification goes away."

Councillor Peter Ewen noted a similar issue with KiwiRail in 2022 when council needed to advance the business case for Westport flood protection: "There was no response".

Councillor Peter Haddock said the crux of the matter was the people of Hokitika "are vulnerable and at risk".

Councillor Andy Campbell noted the new stop bank would benefit them: "We're actually helping them protect their infrastructure for nothing."

In a response, KiwiRail executive general manager property Anna Allen did not directly respond to assertations made at the council table.

However the state rail operator "has worked closely" with the regional council and its consultants on this issue, Allen said.

"Details of the application were received in August last year, and Kiwi Rail requested additional information in September," she said.

KiwiRail then met the consultants for council in October and sought more information afterwards.

"That was provided just after Christmas, and KiwiRail is now reviewing that material. We expect to finish that review shortly."

Allen said KiwiRail wanted to help progress things as quickly as possible but needed "to properly assess" the impact on its rail asset "to ensure it continues to comply with our standards and codes".

* LDR is local body journalism co-funded by RNZ and NZ On Air.

Image
More messages from your neighbours
15 hours ago

Poll: Should all neighbours have to contribute to improvements?

The Team from Neighbourly.co.nz

An Auckland court has ruled a woman doesn’t have to contribute towards the cost of fixing a driveway she shares with 10 neighbours.

When thinking about fences, driveways or tree felling, for example, do you think all neighbours should have to pay if the improvements directly benefit them?

Image
Should all neighbours have to contribute to improvements?
  • 81.6% Yes
    81.6% Complete
  • 15.6% No
    15.6% Complete
  • 2.8% Other - I'll share below
    2.8% Complete
604 votes
1 day ago

Neighbourhood Challenge: Who Can Crack This One?

Riddler from The Neighbourly Riddler

This belongs to you, but everyone else uses it.

Do you think you know the answer to our daily riddle? Don't spoil it for your neighbours! Simply 'Like' this post and we'll post the answer in the comments below at 2pm.

Want to stop seeing riddles in your newsfeed?
Head here and hover on the Following button on the top right of the page (and it will show Unfollow) and then click it. If it is giving you the option to Follow, then you've successfully unfollowed the Riddles page.

Image
3 days ago

What's your favourite tomato recipe?

Mei Leng Wong Reporter from NZ Gardener & Get Growing

Kia ora neighbours. We know your tomato plants are still growing, but we're looking ahead to the harvest already! If you've got a family recipe for tomatoes, we'd love to see it and maybe publish it in our magazine to share with our readers. Send your recipe to mailbox@nzgardener.co.nz, and if we use it in the mag, you will receive a free copy of our February 2025 issue.

Image