T3 Lane Cameras coming to Onewa Road
Auckland Transport are preparing to install 13 CCTV cameras on Onewa Road to allow remote monitoring of the T3 lanes during their hours of operation. The cameras will replace the need for staff to film from the side of the road.
The installation of the Onewa Road cameras will be in two phases:
* Phase 1: The first phase of the works, preparing the pole foundations and cables, is scheduled for late February 2021 and will take up to three weeks to be completed. This will involve drilling at some of the camera locations along Onewa Road.
* Phase 2: The second phase of the works, installing the poles and cameras, is scheduled to start in May 2021 and will take up to one week to be completed.
The cameras should be operational from June. For the first 3 weeks, Auckland Transport will issue warning letters to drivers who use the lane incorrectly. From July (date to be confirmed), $150 infringement fees will be issued.
Today’s Mind-Bender is the Last of the Year! Can You Guess It Before Everyone Else? 🌟🎁🌲
I dance in the sky with green and gold, a spectacle few are lucky to behold; I’m best seen in the south, a celestial sight—what am I, lighting up the New Zealand night?
Do you think you know the answer? Simply 'Like' this post and we'll post the answer in the comments below at 2pm on the day!
Want to stop seeing these in your newsfeed? No worries! Simply head here and click once on the Following button.
No gift? No stress
Let the Christmas elves at Mags4gifts.co.nz handle your last-minute shopping. For a limited time, gift a subscription with up to 40% off best-sellers like TV Guide, NZ House & Garden, and NZ Gardener. It’s the perfect Christmas present, sorted in minutes (and no one needs to know it was a last-minute surprise)!
Loading…