Work to improve Lake Hood water quality ‘looking good’

Nicole Mathewson Reporter from The Press

By local democracy reporter Jonathan Leask:

The first project to improve water flow into a popular Canterbury recreational lake is “looking good so far”.

A new channel to divert water from the existing Ashburton River intake channel to the Lake Hood extension has been completed, as the council works towards improving water quality.

Lake Hood, a made-made lake south of Ashburton, has been plagued by algal blooms in recent years.

Ashburton Ditrsict Council infrastructure and open spaces group manager Neil McCann said a drone was sent up on Sunday and Monday to see how it was working.

“We had some water coming in from the river with some sediment in it so it was really useful to see how it was working.

“Initially, it looks like it’s doing slightly better than we expected.
“It is getting water down to the northwestern canals.

“So far it is looking good.”

The council is attempting to tackle the water quality issues after taking over the management of the lake earlier this year.

The council budgeted $250,000 for water quality improvements in the 2024-25 financial year and the new channel was the first project.
No extra water is being taken from the river.

It is water from the existing water-take consent being split between the new channel and the canal into the original lake at the northern-end beach.

The idea behind the secondary inlet is to help flush the canals on the western side of the lake, McCann said.

Now that it is up and running, it will be monitored to ensure the water is ending up where they want it, he said.

The new channel aims to improve water quality at Lake Hood, with the council committed to investing in long-term solutions, he said.

The council also wants to make improvements at the river intake and is continuing discussions with Environment Canterbury about river water.

The Lake Extension Trust Limited had previously managed the lake and surrounds for the council but since July 1.

Ashburton Contracting Limited has been managing the lake on a five-year contract.

A weed harvester was purchased for around $180,000 earlier this year and Ashburton Contracting Limited staff have been trained to drive it and are expected to start using it in October.

More messages from your neighbours
19 hours ago

2025: The Year of Puzzling It Out!

Riddler from The Neighbourly Riddler

There’s a one-story house where everything is yellow.

The walls are yellow, the doors are yellow, and even the furniture is yellow.

What colour are the stairs?

Do you think you know the answer to our daily riddle? Don't spoil it for your neighbours! Simply 'Like' this post and we'll post the answer in the comments below at 2pm.

Want to stop seeing riddles in your newsfeed?
Head here and hover on the Following button on the top right of the page (and it will show Unfollow) and then click it. If it is giving you the option to Follow, then you've successfully unfollowed the Riddles page.

Image
19 hours ago

Share your summer photos! 📷

The Team from Neighbourly.co.nz

Taken some beautiful snaps lately? Whether it's rainbows, sunsets or a beautiful summer's day, we'd love you to share the joy with us.

Share a photo in the comments below

Image
21 days ago

Poll: Would you rather: Christmas in summer forever or winter forever?

The Team from Neighbourly.co.nz

Just a bit of a fun poll to get you thinking.

If you had to live out your Christmas days, would you prefer it was a summer Christmas or a winter Christmas?

Image
Would you rather: Christmas in summer forever or winter forever?
  • 63.1% Summer
    63.1% Complete
  • 35.5% Winter
    35.5% Complete
  • 1.4% Other - I'll share below
    1.4% Complete
2659 votes