End in sight for year-long roadworks on Christchurch's Colombo St
More than a year of roadworks on one of Christchurch's major streets is almost at an end.
The $4.4 million Christchurch City Council project is installing a new wastewater pipeline along the middle of Colombo St between the roundabout at Dyers Pass Rd and Fisher Ave.
Construction work started on June 5, 2018, and was expected to take 12 months, but has ran slightly over schedule. It will be completed on Wednesday, though some ,more minor work will be done in July.
Poll: Are you starting to feel a lift in business confidence across the Canterbury region?
The Press reports that Canterbury is right in the middle of a construction boom, with activity forecast to peak around 2027 and major investment flowing into transport, water and energy infrastructure.
We want to know: Are you starting to feel a lift in business confidence across the Canterbury region?
-
40% Yes
-
60% No
Scam Alert: Fake information regarding December Bonuses from MSD
The Ministry of Social Development is reporting that fake information is circulating about new ‘December bonuses’ or ‘benefit increases’
If you get suspicious communication, please contact Netsafe.
Loading…