Silverdale Park n Ride bus stop
I sent a message to Auckland Transport re when the actual bus station part was going to be finished.
I got 2 replies stating 2 different things ...
1st reply on 5 July
The second phase is the busway building construction. This is being tendered shortly and is expected to be completed by mid-2019. We are also hoping to add another 90 carparks to the park and ride area during the second phase of stage two. At this time, we are currently waiting on an environment court decision which we can expect in two months.
2nd reply 24 July
Unfortunately the time frame for the construction of the station building has changed primarily due to the delay in finalising the station design and in addition to this a delay in acquiring the resource consent for the additional 90 car parks. The expected construction time frame for the station building is from October 2018 to June 2019.
So the actual bus station part either (a) hasn't been designed yet or (B)the council haven't tendered out for the building of it yet depending on which reply you go with, either way nothing will be done till at least October. But as AKL Transport advised a finish date of June next year I wouldn't be hopeful of anything being done till mid 2019.
There is no reason why they cant complete the building of the station while they argue about the resource consent for the extra 90 car parks. By the time they add the car parks they will wish it was an extra 290...not the short sighted 90 they have planned for now.
"Auckland Council, planning for last decade, in the next decade"
Scam Alert: Fake information regarding December Bonuses from MSD
The Ministry of Social Development is reporting that fake information is circulating about new ‘December bonuses’ or ‘benefit increases’
If you get suspicious communication, please contact Netsafe.
The Summer Kiwi Quiz is back by popular demand
Grab a copy of your local Stuff newspaper between 1 Jan - 28 Jan and participate in the Summer Kiwi Quiz! Test your knowledge, answer the daily New Zealand based questions, and find out how well you know our beautiful country!
Each correct answer will get you one entry into the draw to WIN 1 of 5 Ooni Karu 2 Portable Pizza Oven bundles, valued at $1024! Each bundle includes: an Ooni Karu 2 Multi-Fuel Portable Pizza Oven, Ooni Karu 2 Carry Cover, Ooni 12" Perforated Peel, Ooni Digital Infrared Thermometer and an Ooni Cookbook: Cooking with Ooni. The more answers you enter correctly, the higher your chance of winning. For more information and to submit your answers, click here
The Team at Stuff
Loading…