⚠Dixon Street wastewater update⚠
Following the installation of the temporary above ground pipe, we now need to install a permanent underground pipe which means excavating from the Dixon/Willis intersection along Willis Street to State Highway 1 near Ghuznee Street.
On Monday 13 January 2020 we will start site investigations, locating service in the road and trenching along Willis Street. Pedestrian access along both sides of Willis Street will remain the same.
We are holding a community meeting next week, where we would like to invite businesses owners and residents to discuss the project work. We will have a project engineer, council representatives and local councillors available to answer any questions you may have.
The details for the community meeting are:
Tuesday 14 January, 5.30pm - Conference Centre, St John’s in the City.
Updates on this project will be available at: www.wellingtonwater.co.nz...
What word sums up 2024, neighbours?
If 2020 was the year of lockdowns, banana bread, and WFH (work from home)....
In one word, how would you define 2024?
We're excited to see what you come up with!
We're talking new year resolutions...
Tidying the house before going to bed each night, meditating upon waking or taking the stairs at work.
What’s something quick, or easy, that you started doing that made a major positive change in your life?