Mount Albert project
In late January 2020, following the burst in the two wastewater sludge pipelines buried in a tunnel deep under Mt Albert, Wellington Water engaged engineering firm Stantec to identify repair options and manage the project.
Brian Perry Civil were then engaged as the lead contractor to undertake the enabling works and to manage the other contractors working on site.
A long list of options was quickly whittled down to a shortlist of two options for relining the existing pipes.
From the shortlist SaniTube, from German Company, Amex Sanivar, was selected because it offered the best value for money, could be installed quickly and highly experienced New Zealand agent and installer Hadlee and Brunton was able to undertake the work.
Despite the additional challenge of the global pandemic both pipes were successfully relined by the end of May 2020, thanks to the multi-disciplinary team brought together to deliver this innovative repair.
🪱🐦 When are you the most productive? 🌙🦉
The Post has been diving into our daily habits, and research suggests being an early bird or a night owl isn’t just a choice—it’s biology! We all have that specific time when our brains finally "click" into gear.
This raises a big question for the modern workplace. To get the best out of everyone, should employers accommodate our natural body clocks? This idea is at the heart of the four-day work week and flexible scheduling movements.
We want to hear from you:
1. When does your brain "click" into gear?
2. Would a flexible (or shortened) schedule change the way you work?
Khandallah Village Market 14th March 2026
Now that Summer is all but over, we welcome you to the Autumn Edition of the Khandallah Village Market on the 14th of March.
Feldenkrais Intensive Weekend
A weekend of real "me-time", and an opportunity to discover how this amazing method can help you
Email team@fiw.nz
More on www.feldenkrais.org.nz...
Loading…