Waimakariri Gorge Bridge Update and daytime closure
The guardrail on the southern side of the bridge is complete but cold conditions have slowed progress on the remaining section.
We anticipate a further 10 days will be required before we can shift focus to removing scaffolding and disestablishing the site.
Because work is continuing on the guardrail there will still be short 10 minute closures during the daytime. However, the bridge is open at night without closures.
The slower progress has allowed the completion of other maintenance work to take place - such as cleaning and repairs to take place under the bridge.
We thank you for your patience.
Best way to use leftovers?
I'm sure you've got some excess ham at home or cold roast potatoes.
What are some of your favourite ways to use leftover food from Christmas day? Share below.
Fair play
Whether it’s a playhouse, she shed or teenager’s sleepout, a stencil-painted floor in Resene Clockwork Orange will elevate it from meh to wow. Find out how to create your own with these easy step by step instructions.