Mount Albert project
In late January 2020, following the burst in the two wastewater sludge pipelines buried in a tunnel deep under Mt Albert, Wellington Water engaged engineering firm Stantec to identify repair options and manage the project.
Brian Perry Civil were then engaged as the lead contractor to undertake the enabling works and to manage the other contractors working on site.
A long list of options was quickly whittled down to a shortlist of two options for relining the existing pipes.
From the shortlist SaniTube, from German Company, Amex Sanivar, was selected because it offered the best value for money, could be installed quickly and highly experienced New Zealand agent and installer Hadlee and Brunton was able to undertake the work.
Despite the additional challenge of the global pandemic both pipes were successfully relined by the end of May 2020, thanks to the multi-disciplinary team brought together to deliver this innovative repair.
Poll: How are you feeling about the role of AI in business and everyday life? 🤖💻
The Post reports that nearly two-thirds of business leaders are feeling optimistic about 2026 ... with much of that confidence driven by the rollout of AI.
We want to know: How are you feeling about the growing role of AI in business and everyday life?
-
6.4% Excited
-
72.4% Cautious
-
21.2% Somewhere in between
Scam Alert: Fake information regarding December Bonuses from MSD
The Ministry of Social Development is reporting that fake information is circulating about new ‘December bonuses’ or ‘benefit increases’
If you get suspicious communication, please contact Netsafe.
Take a village tour and enjoy a $50 cafe voucher!*
See what everyday life at a Ryman village is really like - from a range of living options to premium amenities on your doorstep.
*Terms and conditions apply.
Loading…